Print Friendly, PDF & Email

Project Detail

Cedar Point Wind Farm 230kV/34.5kV Substations and Missile Site Capacitor Yard Works

cedar-point-03      cedar-point-01      cedar-point-02

Location: Limon, CO

Description:This project consisted of the construction of the East 230kV/34.5kV substation, the West 230kV/34.5KV substation and the Missile Site Capacitor Yard Works for Cedar Point Wind Energy project.

Work Performed By:  Great Southwestern Construction, Inc., a subsidiary of MYR Group

Completion Date: April 2011