Solar – Garland Solar Project

Location: Rosamond, CA

Description: The Garland Solar Project produces enough clean energy to power approximately 50,000 homes. Completed in Kern County, California on 2,000 acres of land, the Garland Solar Project contains 870,000 polycrystalline photovoltaic solar modules mounted on single-axis tracking tables. These modules deliver power to Southern California Edison (SCE) under a long-term power purchase agreement.

MYR Group subsidiary, CSI Electrical Contractors, Inc. tackled this aggressive build schedule which included the installation and testing of a 34.5 kV medium-voltage system. This system required the use of both overhead poles and underground trench installation methods to distribute the collection system throughout the site.

Completion Date: 2016

Work Performed By: CSI Electrical Contractors, Inc., a subsidiary of MYR Group