Aviation Marker Ball Installation on the Big Eddy-Knight 500kV Transmission Line Transmission
Aviation Marker Ball Installation on the Big Eddy-Knight 500kV Transmission Line |
|
---|---|
Client | Bonneville Power Administration (BPA) |
Completion Date | November 2016 |
Location | The Dalles, Oregon |
Completed by | Sturgeon Electric Company, Inc. |
Sturgeon Electric crews installed 23 aviation marker balls and associated hardware atop BPA’s Big Eddy-Knight 500kV Transmission Line. The project marked the first time a federal nonprofit agency allowed a transmission line contractor to use Class B Human External Cargo (HEC) helicopter methods, which involves flying line workers below a helicopter in an “air chair” to accomplish the required work.