S136 Transmission Structure Replacements Energized
S136 Transmission Structure Replacements |
|
---|---|
Client | Eversource |
Completion Date | 2026 |
Location | New Hampshire |
Completed by | Harlan Electric Company |
Harlan Electric’s scope of work includes the complete rebuild of a 115kV transmission line, including the replacement of 215 structures. Harlan Electric is reconductoring 27 miles of 795 conductor with 1272 through challenging terrain in the White Mountains of New Hampshire, utilizing “D” phase wire stringing techniques under energized conditions.
Case Study: Delivering a Large, Energized Transmission Rebuild Project Safely and Ahead of Schedule