Lotus Solar Farm Clean Energy

Lotus Solar Farm

Client Signal Energy
Completion Date Sept. 2020
Location Madera County, California
Completed by CSI Electrical Contractors, Inc.

CSI Electrical Contractors partnered with Signal Energy to build the 70MW Lotus Solar Farm, nestled in a 375-acre almond grove in Madera County. More than 200 union electricians delivered the project within several months, installing 180,000-plus photovoltaic solar modules, more than 415,000 feet of cable — 45,000-plus feet of AC cable and 370,000-plus feet of DC cable.

Lotus Solar Farm produces and delivers energy to Southern California Edison (SCE) through a 20-year power purchase agreement (PPA) and is expected to reduce carbon emissions by 48,000 metric tons annually.